Grid modernisation is usually reported as a list of announcements. Two recent data sets give a more useful view: a quarterly count of what US states are actually deciding, and India's latest parliamentary figures on how much of the sanctioned smart-metering programme exists in the field. Read together, they show that the policy layer and the deployment layer move at different speeds.
What US states are actually legislating
The NC Clean Energy Technology Center's Q2 2026 edition of The 50 States of Grid Modernization, released on 22 July 2026, counted 481 grid modernization actions in the quarter, plus more than 300 introduced bills. Forty-four states, the District of Columbia and Puerto Rico took action. California, Maryland, Virginia and New Jersey were the most active.
The category counts are the interesting part. Energy storage deployment proposals led with 63 actions, followed by interconnection rules (47), utility business model reforms (46), performance-based energy storage incentives (35), performance-based regulation (32) and smart grid technology deployment (29). In the Q1 2026 edition, the same smart grid technology category stood at 30 actions, with 451 total actions across the quarter. Hardware-centred smart grid deployment is therefore a minority of what regulators handle; rules about storage, interconnection and utility incentives dominate.
Scrutiny of spending, and the move to location-based value
The report names three trends. Utilities are pursuing location-based incentives for distributed energy resources, policymakers are scrutinising utility spending on upgrades, and states are opening wholesale markets to virtual power plants. T&D World's coverage quotes Nick Montoni of the centre: "We're seeing a continued trend towards increased scrutiny on utility investments."
Notable decisions listed include Minnesota regulators approving Xcel Energy's first virtual power plant programme, Maryland's Public Service Commission approving virtual power plant programmes, and the North Carolina Utilities Commission approving dynamic line rating prototypes. Managing Director Autumn Proudlove said location-based incentives are being built into utility programmes, which could reduce the need for other grid investments while giving customers direct financial benefits.
The practical reading is that a grid investment now has to show where on the network it creates value, and that evidence comes from network data rather than from the investment plan itself.
India: sanctioned is not installed
India's position looks different. According to a report on a Minister of State for Power's written reply to Parliament, 7.24 crore smart meters (consumer, distribution transformer and feeder) were installed nationally as of 30 June 2026. Of these, 5.73 crore sit under the Revamped Distribution Sector Scheme (RDSS), against 20.33 crore sanctioned under the scheme: 19.79 crore consumer meters, 52.53 lakh distribution transformer meters and 2.05 lakh feeder meters. The same report notes the scheme's sunset date is currently March 31, 2028.
Simple division puts RDSS installation at roughly 28 per cent of the sanctioned quantity, with about 21 months of scheme life remaining from the 30 June reference date. The publication date of that report could not be confirmed, so the figures are best treated as the official 30 June 2026 position.
The wider RDSS envelope, as described in SolarQuarter's 11 August 2026 summary of the same Rajya Sabha reply, includes about ₹1.53 lakh crore sanctioned for loss-reduction infrastructure and about ₹1.31 lakh crore for smart metering, with ₹47,124 crore released since FY2022-23 across 28 states and 45 distribution utilities. It also lists ₹2,627 crore for SCADA and distribution management systems across 394 towns and ₹3,999 crore for IT and operational technology upgrades including ERP and GIS mapping.
What it means for utilities
Two lessons carry across both markets.
- Spending will be audited against outcomes. US regulators are explicitly scrutinising utility investment, and India's RDSS releases are milestone-linked. Programmes that cannot show network-level results will struggle to defend budgets.
- Meters are the start of the data layer, not the end. SCADA, distribution management, GIS and ERP lines in the RDSS budget are the systems that turn meter reads into feeder-level decisions. Utilities that track only meter counts will not see whether those systems are doing their job.
- Location matters. Location-based DER incentives and dynamic line rating both depend on accurate network models and asset data. DISCOMs with poor consumer-to-transformer mapping will find that harder to adopt later.
- Time is the scarce input. With the sunset date set at March 2028, DISCOMs must sequence installation, communications and data integration in parallel rather than one after another.
Key takeaways
- US states logged 481 grid modernization actions in Q2 2026, with storage, interconnection and utility business model reform ahead of smart grid technology deployment (29 actions).
- Regulators are shifting from approving investment to scrutinising it, and rewarding location-specific value.
- India had 7.24 crore smart meters installed as of 30 June 2026, with 5.73 crore under RDSS against 20.33 crore sanctioned, about 28 per cent.
- The RDSS sunset date of March 31, 2028 makes the data and operations layers, not meter shipments, the real schedule risk.
- Watch the next quarterly tracker and the next parliamentary reply for whether deployment and policy are converging.
Sources
- The 50 States of Grid Modernization, Q2 2026 edition (NC Clean Energy Technology Center)
- Report: 44 States Advanced Grid Modernization Policies in Q2 2026 (T&D World)
- The 50 States of Grid Modernization, Q1 2026 edition (NC Clean Energy Technology Center)
- India's smart meter population at 7.24 crore: Parliament (TND India)
- India accelerates power distribution digitalization (SolarQuarter)
Enjoyed this? Get the next one by email